Renewable Energy Case Study — Middle East — 100 MWAC PV Plant

Solar Booster Substation, Desert Site — Middle East — 100 MWAC PV Plant

A 100 MWAC utility solar plant in the desert had a hard, finance-driven grid-connection COD. The inverter supplier's schedule was the critical path everyone watched — but the MV collection and booster substation could just as easily have sunk the date if it had arrived late or failed SAT.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
Solar Booster Substation, Desert Site — Middle East — 100 MWAC PV Plant

Project Overview

Funator took responsibility for the entire collection network hardware: 16 × MVnex 36kV panels, 8 inverter-skid LV packages, and the protection settings for an inverter-dominated grid — engineered for +52 °C summers and sandstorm conditions.

The Challenge

Desert PV plants punish weak engineering twice — at commissioning and for 25 years after:

  • +52 °C summer ambient: standard derating curves would have left the plant short of nameplate capacity exactly when generation is most valuable.
  • Sand ingress: fine desert dust penetrates ordinary IP4X ventilation and grinds down mechanisms; IP54 with sand-filtered ventilation was non-negotiable.
  • Inverter-fed protection: fault currents a fraction of conventional grids make standard overcurrent settings blind — protection had to be engineered for the actual network.

The Solution

MVnex 36kV panels were specified with IP54 enclosures, sand-filter ventilation and C4 corrosion protection, with busbars derated for the site ambient. On the protection side, Sepam relays were configured with directional elements, ROCOF and vector-shift islanding detection, reverse-power logic and voltage/frequency ride-through settings matched to the grid code — parameter sheets delivered with the FAT reports.

Equipment Qty / Configuration Key Ratings
MVnex 36kV switchgear 16 × panels 2500 A · 31.5 kA/3s · IP54 + sand filters
Inverter-skid LV packages 8 × packages Blokset Form 4b · skid-integrated
Protection relays Sepam/MiCOM Grid-code settings · FAT-verified
Collector interface RMU feeder sets Pad-mount · SCADA/IEC 61850

Execution & Delivery

  • Months 1–2: engineering freeze, relay settings study and grid-code compliance review with the owner's consultant.
  • Months 3–5: three staggered dispatches matched to skid erection sequence; FAT reports and relay parameter sheets issued before each shipment.
  • Month 6: pre-commissioning checks, protection injection tests, grid-code compliance verification — energization on the original COD.

Results

  • Energized on the original grid-connection COD; SAT passed on the first attempt with zero NCRs.
  • When the inverter supplier slipped two weeks, the already-on-site, FAT-approved switchgear absorbed the delay — the COD held.
  • First-year availability of the collection network: no switchgear-attributed outages.
“Our inverter supplier was two weeks late but the switchgear was already on site and FAT-approved. That margin saved our COD.” — Project Director, EPC contractor
Explore the Renewable Energy solution Configuration guidance, standards and product lineup for this industry.
Renewable Solution