Infrastructure Case Study — East Africa — International Airport

Airport Terminal MV/LV Power Distribution — East Africa — International Airport

A greenfield international airport terminal in East Africa was being built in three civil phases over 18 months, and its electrical backbone had to track that programme exactly. Over-early delivery would mean unpaid equipment sitting in a dusty, security-sensitive site; late delivery would put the commissioning of boarding bridges, baggage systems and life-safety loads at risk.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
Airport Terminal MV/LV Power Distribution — East Africa — International Airport

Project Overview

Funator contracted for the complete MV/LV scope — 24 × MVnex 24kV panels and 48 × Blokset LV panels — as a single-source package with phased delivery, FAT evidence and on-site commissioning support.

The Challenge

Airport projects add layers that ordinary buildings do not have:

  • Zero-tolerance public safety: an electrical fault in a terminal is a security and continuity event, so Form 4b separation and arc-flash mitigation were specified without compromise.
  • Phased construction: the electrical rooms were handed over phase-by-phase; each delivery had to match its room's readiness, not the factory's convenience.
  • Consultant scrutiny: the owner's engineer reviewed every type-test report and FAT record before allowing each dispatch — documentation quality was as decisive as the equipment itself.

The Solution

We planned three delivery tranches mapped to the civil milestones, each FAT-tested and documented as a self-contained package: type-test certificates, FAT reports and FAT video recordings delivered with the shipping documents. A Funator commissioning engineer attended each phase's SAT, so the same engineering context carried through from factory to handover.

Equipment Qty / Configuration Key Ratings
MVnex 24kV switchgear 24 × panels 2000 A · 31.5 kA/3s · arc-flash mitigation
Blokset LV switchboards 48 × panels Form 4b · essential/normal segregation
Protection relays Sepam package ATS logic for dual incomer + bus coupler
Documentation Full compliance pack Type tests · FAT video · SAT records

Execution & Delivery

  • Phase 1: main intake substation — 12 × MVnex + 24 × Blokset, delivered two weeks ahead of the room handover.
  • Phase 2: pier distribution — 8 × MVnex + 16 × Blokset, FAT-approved before the containers left the factory.
  • Phase 3: satellite extension — 4 × MVnex + 8 × Blokset, dispatched after night-flight restrictions were confirmed for crane lifts.
  • Each phase: SAT attended by Funator engineer; NCR register reviewed and closed before energization.

Results

  • All 3 phases passed SAT on the first attempt — 72 units, zero non-conformances.
  • Phase 1 arrived two weeks early, giving the integrator headroom that was later consumed by civil delays without affecting the energization date.
  • The terminal energization and trial operations stayed on the master programme.
“Funator delivered Phase 1 two weeks ahead of schedule. The FAT video documentation and IEC test reports arrived before the containers — our consultant approved everything without a single query.” — Lead Electrical Engineer, owner's engineer team