Oil & Gas Case Study — Europe — Refinery

12kV Refinery Switchroom Expansion — Europe — Refinery

A European refinery was adding a new process unit and needed to expand its 11kV main distribution switchroom — while every existing feeder stayed live. The switchroom sits in the heart of the plant, surrounded by classified zones, which ruled out any hot work during normal operation and made logistics a planning exercise in itself.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
12kV Refinery Switchroom Expansion — Europe — Refinery

Project Overview

Funator engineered the expansion as a Blokset Form 4b lineup adjacent to the existing switchboard, with six tie-in connections to the live busbar system executed under permit-to-work controls.

The Challenge

The defining risks were operational, not technical:

  • Live 11kV bus throughout: every tie-in required safety case approval, insulated tooling, and a rehearsed switching sequence.
  • Classified area logistics: equipment had to be moved in and positioned without hot work, using cold-cutting and pre-fabricated supports.
  • No spare capacity for error: a failed tie-in would have meant re-scheduling production units around a second attempt.

The Solution

The Blokset Form 4b lineup was factory-built and pre-commissioned to the maximum extent possible, then split into transport sections. On site, the six tie-ins were executed in planned windows — each rehearsed on paper the day before, with the operations team signing off each step. Insulated busbar connection kits and temporary earths were staged for every window.

Equipment Qty / Configuration Key Ratings
Blokset LV/MV lineup Form 4b 4000 A busbar · internal separation Form 4b
Tie-in connection kits 6 × sets Insulated bolted links · rated for live work
Protection & metering Full package IEC 61439 verification + SAT records
Documentation As-built + method statements Per-window switching schedules

Execution & Delivery

  • Pre-stage: lineup erected, primary and secondary testing completed offline.
  • Windows 1–6: six tie-ins over three months, each executed inside a 6-hour window with full operational sign-off.
  • Close-out: final inspection by the authority having jurisdiction — passed first attempt.

Results

  • Zero-downtime cutover: production was unaffected across all six tie-in windows.
  • First-attempt inspection pass — no rectification list.
  • The expanded switchroom now carries the new process unit with documented spare ways for future growth.The expanded switchroom now carries the new process unit with documented spare ways for future growth.