Oil & Gas Case Study — Middle East — Oman

24kV Gas Gathering Retrofit — Middle East — Oman

A gas processing plant on the Omani coast needed to replace its aging 24kV switchyard while keeping production running. The existing switchgear had reached end of useful life, spare parts were unobtainable, and every tie-in to the live 24kV bus had to be executed inside narrow scheduled shutdown windows.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
24kV Gas Gathering Retrofit — Middle East — Oman

Project Overview

Funator supplied 14 × PIX 24kV panels with C5-M marine-grade protection — essential on a site 800 m from the sea — and planned the phased cutover jointly with the plant's operations team.

The Challenge

Retrofit in a live plant is a different discipline from greenfield:

  • No production interruption permitted: each tie-in window was capped at 8 hours, with gas export commitments unaffected.
  • Coastal C5-M corrosion category: standard coatings would fail within years; every enclosure, bolt and busbar joint needed marine-grade protection.
  • Legacy interface risk: old protection settings and CT ratios had to be mapped panel-by-panel before demolition to avoid protection blind spots during cutover.

The Solution

PIX air-insulated switchgear was selected for its short-circuit withstand and compact footprint, allowing the new lineup to be erected in stages alongside the old one. Each panel was factory-configured with its final settings, and the cutover sequence was rehearsed on a point-by-point schedule: isolation, CT/VT transfer, protection injection, then re-energization within the window.

Equipment Qty / Configuration Key Ratings
PIX 24kV switchgear 14 × panels 2500 A · 31.5 kA/3s · C5-M coating
Protection relays 14 × Sepam Settings migrated & pre-loaded per panel
Busbar system Single busbar Partially sectioned per cutover stage
Specials Marine-grade hardware A4-80 bolts · sealed CT chambers

Execution & Delivery

  • Stage 1: new lineup erected in a pre-cleared bay; primary injection and settings verification offline.
  • Stage 2–4: three 8-hour tie-in windows executed on consecutive weekends, each returning the plant to full operation before Monday.
  • Stage 5: old switchgear de-energized, decommissioned and removed; final SAT and as-built documentation issued.

Results

  • Energized 11 days ahead of the contractual completion date.
  • Zero unplanned outages or production losses during the entire cutover program.
  • Protection coordination verified by third-party study — no nuisance trips in the first year of operation.