Project Overview
Funator supplied 14 × PIX 24kV panels with C5-M marine-grade protection — essential on a site 800 m from the sea — and planned the phased cutover jointly with the plant's operations team.
The Challenge
Retrofit in a live plant is a different discipline from greenfield:
- No production interruption permitted: each tie-in window was capped at 8 hours, with gas export commitments unaffected.
- Coastal C5-M corrosion category: standard coatings would fail within years; every enclosure, bolt and busbar joint needed marine-grade protection.
- Legacy interface risk: old protection settings and CT ratios had to be mapped panel-by-panel before demolition to avoid protection blind spots during cutover.
The Solution
PIX air-insulated switchgear was selected for its short-circuit withstand and compact footprint, allowing the new lineup to be erected in stages alongside the old one. Each panel was factory-configured with its final settings, and the cutover sequence was rehearsed on a point-by-point schedule: isolation, CT/VT transfer, protection injection, then re-energization within the window.
| Equipment | Qty / Configuration | Key Ratings |
|---|---|---|
| PIX 24kV switchgear | 14 × panels | 2500 A · 31.5 kA/3s · C5-M coating |
| Protection relays | 14 × Sepam | Settings migrated & pre-loaded per panel |
| Busbar system | Single busbar | Partially sectioned per cutover stage |
| Specials | Marine-grade hardware | A4-80 bolts · sealed CT chambers |
Execution & Delivery
- Stage 1: new lineup erected in a pre-cleared bay; primary injection and settings verification offline.
- Stage 2–4: three 8-hour tie-in windows executed on consecutive weekends, each returning the plant to full operation before Monday.
- Stage 5: old switchgear de-energized, decommissioned and removed; final SAT and as-built documentation issued.
Results
- Energized 11 days ahead of the contractual completion date.
- Zero unplanned outages or production losses during the entire cutover program.
- Protection coordination verified by third-party study — no nuisance trips in the first year of operation.