Oil & Gas Case Study — Middle East — Iraq

11kV Desert Substation Package — Middle East — Iraq

An onshore oil field development in southern Iraq needed a new 11kV distribution substation to feed early-production facilities — wellhead pumps, separation skids and camp power. The site is remote: the nearest major city is a full day's drive, summer temperatures exceed 50 °C, and logistics run through a single access road that floods in winter.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
11kV Desert Substation Package — Middle East — Iraq

Project Overview

The operator's engineering team specified Schneider equipment for its service network in the region, and engaged Funator to package, FAT-test and deliver the complete substation as plug-and-play containerized units.

The Challenge

The project constraints were dominated by location:

  • Remote desert site with no local support — a failed component could take weeks to replace, so reliability and spares had to be engineered in from the start.
  • Aggressive early-production schedule: the substation had to be energized within weeks of the skids arriving, leaving no room for site assembly or rework.
  • Harsh environment: airborne sand, 50 °C+ ambient, and winter humidity required enclosure and coating selections well beyond the catalogue default.

The Solution

We delivered the substation as two factory-integrated containers: one housing 8 × MVnex 12kV panels with a duplex transformer interface, the other 6 × SM6 ring main units for the wellhead feeders. Both were wired, interlocked and FAT-tested as one system before dispatch — site work limited to positioning onto plinths, cabling between containers, and termination.

Equipment Qty / Configuration Key Ratings
MVnex 12kV switchgear 8 × panels 1250 A · 31.5 kA/3s · IP4X containerized
SM6 ring main units 6 × units 630 A · SF6-insulated · surge-arrested feeders
Package transformers 2 × 2.5 MVA ONAN · 50 °C rise · sand-filter breathers
Spares packageSpares package 2-year O&M kit Interrupters, fuses, indicators, gaskets

Execution & Delivery

  • Week 1–2: single-line and protection coordination approved with the operator's consultants.
  • Week 3–7: container integration, wiring, interlock testing; FAT witnessed remotely via video with the full test protocol recorded.
  • Week 8–9: dispatch with incoterms to site access point; installation supervised by a Funator commissioning engineer.
  • Week 10: energized and handed over with SAT documentation pack.

Results

  • 9 weeks order-to-dispatch — against a 16-week regional norm for comparable packages.
  • 100% first-pass FAT: every test item passed without rectification or retest.
  • Energized on schedule; early production started without power-related delay.