Project Overview
The operator's engineering team specified Schneider equipment for its service network in the region, and engaged Funator to package, FAT-test and deliver the complete substation as plug-and-play containerized units.
The Challenge
The project constraints were dominated by location:
- Remote desert site with no local support — a failed component could take weeks to replace, so reliability and spares had to be engineered in from the start.
- Aggressive early-production schedule: the substation had to be energized within weeks of the skids arriving, leaving no room for site assembly or rework.
- Harsh environment: airborne sand, 50 °C+ ambient, and winter humidity required enclosure and coating selections well beyond the catalogue default.
The Solution
We delivered the substation as two factory-integrated containers: one housing 8 × MVnex 12kV panels with a duplex transformer interface, the other 6 × SM6 ring main units for the wellhead feeders. Both were wired, interlocked and FAT-tested as one system before dispatch — site work limited to positioning onto plinths, cabling between containers, and termination.
| Equipment | Qty / Configuration | Key Ratings |
|---|---|---|
| MVnex 12kV switchgear | 8 × panels | 1250 A · 31.5 kA/3s · IP4X containerized |
| SM6 ring main units | 6 × units | 630 A · SF6-insulated · surge-arrested feeders |
| Package transformers | 2 × 2.5 MVA | ONAN · 50 °C rise · sand-filter breathers |
| Spares packageSpares package | 2-year O&M kit | Interrupters, fuses, indicators, gaskets |
Execution & Delivery
- Week 1–2: single-line and protection coordination approved with the operator's consultants.
- Week 3–7: container integration, wiring, interlock testing; FAT witnessed remotely via video with the full test protocol recorded.
- Week 8–9: dispatch with incoterms to site access point; installation supervised by a Funator commissioning engineer.
- Week 10: energized and handed over with SAT documentation pack.
Results
- 9 weeks order-to-dispatch — against a 16-week regional norm for comparable packages.
- 100% first-pass FAT: every test item passed without rectification or retest.
- Energized on schedule; early production started without power-related delay.