Project Overview
Funator was contracted to engineer, supply and commission the LV distribution backbone: Blokset switchgear, prefabricated e-houses, and the monitoring package — all FAT-tested before dispatch and documented to the owner's Tier III/IV audit standards.
The Challenge
Three constraints defined the project from day one:
- 50 °C continuous ambient with no derating allowed — standard catalogue ratings assume 40 °C, so every busbar, breaker and CT had to be re-rated for the site.
- 12-week total window from PO to energization, with the civil pad ready only 4 weeks before the deadline — everything had to ship FAT-approved, leaving zero site-debug margin.
- Tier III/IV compliance audit — the owner's engineering team required complete type-test evidence, arc-flash study inputs and Form 4b separation documentation before energization.
The Solution
We engineered the module around the site, not the catalogue. Blokset Form 4b enclosures were specified with forced-ventilation channels, high-conductivity busbars sized for +50 °C, and pre-integrated EcoStruxure thermal-monitoring sensors reporting to the BMS. The assembly was built and FAT-tested as a single factory-integrated e-house, so site work was reduced to positioning, glanding and termination.
| Equipment | Qty / Configuration | Key Ratings |
|---|---|---|
| Blokset LV switchboard | 2 × Form 4b lineups | 6300 A · 80 kA/1s · IP54 desert-rated |
| Prefabricated e-house | 4 × modules | Forced ventilation · sand-filter HVAC · 50 °C rated |
| EcoStruxure sensors | 96 × thermal points | Busbar + breaker monitoring, BMS-integrated |
| MVnex 12.8kV switchgear | 1 × ring-main room | Dual-source ring · IAC AFLR classified |
Execution & Delivery
- Week 1–3: engineering freeze — thermal derating calculation, arc-flash study inputs, single-line and layout approval by owner.
- Week 4–8: factory assembly and integration; FAT with owner witness, including temperature-rise test at elevated ambient.
- Week 9–10: split shipments by sea and air freight; site team mobilized in parallel.
- Week 11–12: positioning, termination, cold testing and energization — SAT signed on day 83 from PO.
Results
- Energized 2 days ahead of the 12-week deadline, protecting the rack-in date.
- 2+ years of operation with zero switchgear downtime; thermal monitoring has flagged and pre-empted two loose-connection issues before failure.2+ years of operation with zero switchgear downtime; thermal monitoring has flagged and pre-empted two loose-connection issues before failure.
- Facility PUE of 1.25, with the power module's monitored losses feeding the efficiency model.
“The engineering team solved our temperature derating problem in the design phase, not on site.” — Owner's Senior Electrical Engineer, hyperscale campus, Riyadh