Data Center Case Study — Middle East — Saudi Arabia

Hyperscale Data Center Power Module — Middle East — Saudi Arabia

A hyperscale colocation campus under construction outside Riyadh needed its first 20 MW power module energized before the server-hall fit-out could begin. The owner's program left a 12-week window between substation handover and first customer rack-in — in a location where summer ambient temperatures reach 50 °C and sandstorms are a design condition, not an exception.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
Hyperscale Data Center Power Module — Middle East — Saudi Arabia

Project Overview

Funator was contracted to engineer, supply and commission the LV distribution backbone: Blokset switchgear, prefabricated e-houses, and the monitoring package — all FAT-tested before dispatch and documented to the owner's Tier III/IV audit standards.

The Challenge

Three constraints defined the project from day one:

  • 50 °C continuous ambient with no derating allowed — standard catalogue ratings assume 40 °C, so every busbar, breaker and CT had to be re-rated for the site.
  • 12-week total window from PO to energization, with the civil pad ready only 4 weeks before the deadline — everything had to ship FAT-approved, leaving zero site-debug margin.
  • Tier III/IV compliance audit — the owner's engineering team required complete type-test evidence, arc-flash study inputs and Form 4b separation documentation before energization.

The Solution

We engineered the module around the site, not the catalogue. Blokset Form 4b enclosures were specified with forced-ventilation channels, high-conductivity busbars sized for +50 °C, and pre-integrated EcoStruxure thermal-monitoring sensors reporting to the BMS. The assembly was built and FAT-tested as a single factory-integrated e-house, so site work was reduced to positioning, glanding and termination.

Equipment Qty / Configuration Key Ratings
Blokset LV switchboard 2 × Form 4b lineups 6300 A · 80 kA/1s · IP54 desert-rated
Prefabricated e-house 4 × modules Forced ventilation · sand-filter HVAC · 50 °C rated
EcoStruxure sensors 96 × thermal points Busbar + breaker monitoring, BMS-integrated
MVnex 12.8kV switchgear 1 × ring-main room Dual-source ring · IAC AFLR classified
Hyperscale Data Center Power Module

Execution & Delivery

  • Week 1–3: engineering freeze — thermal derating calculation, arc-flash study inputs, single-line and layout approval by owner.
  • Week 4–8: factory assembly and integration; FAT with owner witness, including temperature-rise test at elevated ambient.
  • Week 9–10: split shipments by sea and air freight; site team mobilized in parallel.
  • Week 11–12: positioning, termination, cold testing and energization — SAT signed on day 83 from PO.

Results

  • Energized 2 days ahead of the 12-week deadline, protecting the rack-in date.
  • 2+ years of operation with zero switchgear downtime; thermal monitoring has flagged and pre-empted two loose-connection issues before failure.2+ years of operation with zero switchgear downtime; thermal monitoring has flagged and pre-empted two loose-connection issues before failure.
  • Facility PUE of 1.25, with the power module's monitored losses feeding the efficiency model.
“The engineering team solved our temperature derating problem in the design phase, not on site.” — Owner's Senior Electrical Engineer, hyperscale campus, Riyadh
Explore the Renewable Energy solution Configuration guidance, standards and product lineup for this industry.
Renewable Solution