Project Overview
Funator drew on Heji Group's 5,000+ unit ready stock to supply over 200 MVnex panels in a phased sequence matched to the erection programme.
The Challenge
The timeline was the project:The timeline was the project:
- 200+ panels against a 6-month regional norm — the programme could not wait.
- Import logistics: port congestion and inland transport required split shipments with careful sequencing.
- Utility inspection regime: every panel needed complete factory documentation for utility acceptance testing.
The Solution
Ready-stock MVnex panels were inspected, configured and released in three tranches: incomer and bus-section panels first, then feeders in erection order, finally spares and ancillaries. Each tranche shipped with its full documentation pack — type tests, routine tests, wiring diagrams — so utility inspectors could clear panels as they arrived.
| Equipment | Qty / Configuration | Key Ratings |
|---|---|---|
| MVnex 12kV panels | 200+ units | From Heji Group ready stock · inspected & re-certified |
| Protection relays | Full substation set | Settings to utility specification |
| Busbars & ancillaries | Complete package | Galvanized supports · connectors · labels |
| Documentation | Utility acceptance pack | Per-panel routine test certificates |
Execution & Delivery
- Tranche 1 (day 10): incomers and bus sections on site.
- Tranche 2 (day 18): feeder panels in erection sequence.
- Tranche 3 (day 25): spares, relays and ancillaries — complete scope delivered.
- Utility acceptance testing ran in parallel with erection; energization followed within weeks.
Results
- Complete delivery in 25 days against a 6-month norm — project timeline shortened by 30%.
- All panels cleared utility inspection without documentation queries.
- Substation energized before the rainy-season peak as programmed.
“Funator delivered genuine panels faster than any regional supplier we have worked with.” — Project Manager, state transmission programme