Power & Energy Case Study — Africa — Nigeria

110kV Substation Project — Africa — Nigeria

A state utility transmission programme required a new 110kV substation to relieve an overloaded urban network before the rainy season peak. More than 200 MV panels were needed, the grid-connection date was set by a national programme — and local suppliers quoted 6-month lead times.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
110kV Substation Project — Africa — Nigeria

Project Overview

Funator drew on Heji Group's 5,000+ unit ready stock to supply over 200 MVnex panels in a phased sequence matched to the erection programme.

The Challenge

The timeline was the project:The timeline was the project:

  • 200+ panels against a 6-month regional norm — the programme could not wait.
  • Import logistics: port congestion and inland transport required split shipments with careful sequencing.
  • Utility inspection regime: every panel needed complete factory documentation for utility acceptance testing.

The Solution

Ready-stock MVnex panels were inspected, configured and released in three tranches: incomer and bus-section panels first, then feeders in erection order, finally spares and ancillaries. Each tranche shipped with its full documentation pack — type tests, routine tests, wiring diagrams — so utility inspectors could clear panels as they arrived.

Equipment Qty / Configuration Key Ratings
MVnex 12kV panels 200+ units From Heji Group ready stock · inspected & re-certified
Protection relays Full substation set Settings to utility specification
Busbars & ancillaries Complete package Galvanized supports · connectors · labels
Documentation Utility acceptance pack Per-panel routine test certificates

Execution & Delivery

  • Tranche 1 (day 10): incomers and bus sections on site.
  • Tranche 2 (day 18): feeder panels in erection sequence.
  • Tranche 3 (day 25): spares, relays and ancillaries — complete scope delivered.
  • Utility acceptance testing ran in parallel with erection; energization followed within weeks.

Results

  • Complete delivery in 25 days against a 6-month norm — project timeline shortened by 30%.
  • All panels cleared utility inspection without documentation queries.
  • Substation energized before the rainy-season peak as programmed.