Infrastructure Case Study — West Africa — Container Terminal

Container Terminal Quayside Power — West Africa — Container Terminal

A container terminal expanding from 600,000 to 1.2 million TEU per year needed quayside electrical infrastructure for four new ship-to-shore cranes plus reefer racks — in one of the most corrosive environments electrical equipment can face: salt fog, monsoon humidity and iron-ore dust, three seasons a year.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
Container Terminal Quayside Power — West Africa — Container Terminal

Project Overview

Funator delivered the outdoor MV kiosk line-up and Blokset LV distribution, engineered for C5-M marine duty and the regenerative load cycles of modern crane drives.

The Challenge

Ports are where switchgear goes to die — unless specified honestly:

  • C5-M corrosion category: salt-laden atmosphere plus ore dust requires marine-grade coating systems, sealed enclosures and anti-condensation control.
  • Crane duty cycling: regenerative drives push power back into the network, demanding switchgear and protection rated for bidirectional flow.
  • Terminal schedule: the cranes had a fixed arrival date on a single vessel — the electrical infrastructure had to be tested and waiting.

The Solution

MVnex 36kV was supplied in outdoor kiosk form with C5-M coating systems, anti-condensation heaters and filtered ventilation. Blokset LV switchboards fed the crane busbars with active harmonic filter interfaces, and protection was configured for regenerative feedback with directional supervision on the feeder relays.

Equipment Qty / Configuration Key Ratings
MVnex 36kV outdoor kiosks 6 × kiosks C5-M marine coating · IP54 · anti-condensation
Blokset LV switchboards 18 × panels Crane feeders · Form 4b · filter interface
Active harmonic filters 4 × sets THD compliance on regenerative crane bus
Reefer rack distribution 8 × stations Weatherproof · metering per rack row

Execution & Delivery

  • Months 1–3: kiosk design and coating-system certification; harmonic study for the crane drive profile.
  • Months 4–6: factory assembly; salt-spray and coating-thickness certification documented for the port authority.
  • Month 7: delivery timed to crane vessel arrival; installation and termination alongside crane rail works.
  • Month 8: staged energization, crane load tests and SAT with the terminal operator.

Results

  • All four cranes load-tested and accepted within a week of the vessel berthing.
  • First monsoon season completed with zero corrosion findings at the annual inspection.
  • Reefer capacity doubled as programmed, with per-rack metering feeding the terminal's billing system.
“Salt air destroys cheap switchgear in two years. After the first monsoon, this still looks new — and the coating certificates satisfied our port authority's surveyor.” — Chief Engineer, terminal operator