Infrastructure Case Study — Middle East — Gulf

Large Hospital Essential Power System — Middle East — Gulf

A 400-bed hospital campus was replacing its 30-year-old electrical backbone while the existing hospital stayed fully operational — including ICU, surgery and emergency departments that cannot tolerate even a documented millisecond break beyond the UPS ride-through.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
Large Hospital Essential Power System — Middle East — Gulf

Project Overview

Funator supplied the new MV and LV distribution, the medical IT monitoring infrastructure and the cutover engineering for the transfer weekend, working to IEC 60364-7-710 medical-location requirements throughout.

The Challenge

Hospital power is a life-safety system, not a utility:

  • IEC 60364-7-710 medical locations: Group 2 rooms (operating theatres, ICUs) required medical IT supplies with insulation monitoring and redundancy.
  • Zero-interruption cutover: patient transfer weekend demanded a rehearsed sequence across essential, non-essential and safety loads, with generator and UPS bridging.
  • Authority approval: the health authority's inspector required complete IEC documentation and test records before issuing the occupancy permit for the new wing.

The Solution

MVnex 24kV formed the medium-voltage backbone with dual incomers and bus coupler logic. On the LV side, PrismaSeT switchboards provided Form 4b separation between essential and non-essential buses, with medical IT isolation monitors on every Group 2 circuit and LSZH materials throughout. The cutover sequence was rehearsed twice on paper and once electrically with temporary bridging supplies.

Equipment Qty / Configuration Key Ratings
MVnex 24kV switchgear 8 × panels 2000 A · 31.5 kA/3s · ATS logic
PrismaSeT LV switchboards 24 × panels Form 4b · essential/non-essential segregation
Medical IT system 40 × rooms Isolation monitoring · insulation fault location
UPS & generator interface Full bridge Static bypass coordination · LSZH cabling

Execution & Delivery

  • Phase 1: new wing energized as a dead system — primary injection, insulation tests and IT-monitor verification.
  • Phase 2: dry-run cutover rehearsal with the facilities team, including generator load-shed tables and UPS battery autonomy checks.
  • Phase 3: patient transfer weekend — eight staged cutovers across 36 hours, each returning circuits to normal supply before the next stage.
  • Phase 4: health authority inspection with full IEC test documentation; occupancy permit issued without conditions.

Results

  • Patient transfer weekend completed with zero supply interruptions on any critical circuit.
  • Health authority inspection passed first time, with the IT-system documentation cited as exemplary.
  • New wing operational on schedule; legacy system decommissioned and removed two weeks later.
“Patient transfer weekend was flawless — not a single supply interruption on any critical circuit. The rehearsal discipline Funator brought made the difference.” — Director of Facilities, hospital group