Project Overview
Funator supplied the new MV and LV distribution, the medical IT monitoring infrastructure and the cutover engineering for the transfer weekend, working to IEC 60364-7-710 medical-location requirements throughout.
The Challenge
Hospital power is a life-safety system, not a utility:
- IEC 60364-7-710 medical locations: Group 2 rooms (operating theatres, ICUs) required medical IT supplies with insulation monitoring and redundancy.
- Zero-interruption cutover: patient transfer weekend demanded a rehearsed sequence across essential, non-essential and safety loads, with generator and UPS bridging.
- Authority approval: the health authority's inspector required complete IEC documentation and test records before issuing the occupancy permit for the new wing.
The Solution
MVnex 24kV formed the medium-voltage backbone with dual incomers and bus coupler logic. On the LV side, PrismaSeT switchboards provided Form 4b separation between essential and non-essential buses, with medical IT isolation monitors on every Group 2 circuit and LSZH materials throughout. The cutover sequence was rehearsed twice on paper and once electrically with temporary bridging supplies.
| Equipment | Qty / Configuration | Key Ratings |
|---|---|---|
| MVnex 24kV switchgear | 8 × panels | 2000 A · 31.5 kA/3s · ATS logic |
| PrismaSeT LV switchboards | 24 × panels | Form 4b · essential/non-essential segregation |
| Medical IT system | 40 × rooms | Isolation monitoring · insulation fault location |
| UPS & generator interface | Full bridge | Static bypass coordination · LSZH cabling |
Execution & Delivery
- Phase 1: new wing energized as a dead system — primary injection, insulation tests and IT-monitor verification.
- Phase 2: dry-run cutover rehearsal with the facilities team, including generator load-shed tables and UPS battery autonomy checks.
- Phase 3: patient transfer weekend — eight staged cutovers across 36 hours, each returning circuits to normal supply before the next stage.
- Phase 4: health authority inspection with full IEC test documentation; occupancy permit issued without conditions.
Results
- Patient transfer weekend completed with zero supply interruptions on any critical circuit.
- Health authority inspection passed first time, with the IT-system documentation cited as exemplary.
- New wing operational on schedule; legacy system decommissioned and removed two weeks later.
“Patient transfer weekend was flawless — not a single supply interruption on any critical circuit. The rehearsal discipline Funator brought made the difference.” — Director of Facilities, hospital group