Project Overview
Funator supplied the MV interconnection and LV switchboards interfacing the battery containers — plus the documentation package the lender's technical advisor required before financial close of the operation phase.
The Challenge
BESS electrical packages have their own physics:
- Bidirectional rapid duty: the switchgear sees full-power reversal several times per hour — thermal cycling and protection coordination must be designed for it, not assumed.
- Arc-flash exposure: DC-side fault energy plus inverter contribution demanded a documented arc-flash mitigation approach from day one.
- Lender documentation: UL 9540 / IEC 62933-aligned declarations, witnessed FAT and metering-point definitions were conditions of financial close.
The Solution
Okken LV switchboards were configured for the skid interfaces, rated for the rapid duty cycle with temperature-monitored connections. MVnex 33kV panels connected the plant to the grid with directional protection and anti-islanding logic coordinated with the inverters' grid-forming controls. SGS witnessed the FAT, and the complete compliance pack was issued before shipment.
| Equipment | Qty / Configuration | Key Ratings |
|---|---|---|
| Okken LV switchboardsOkken LV switchboards | 6 × skids | Up to 5000 A · rapid-duty rated · thermal monitoring |
| MVnex 33kV switchgear | 4 × panels | 1250 A · 31.5 kA/3s · directional protection |
| Sepam / MiCOM relays | Protection suite | Anti-islanding · ROCOF · intertrip with EMS |
| Compliance package | UL 9540 / IEC 62933 | Witnessed FAT · metering points · arc-flash study |
Execution & Delivery
- Months 1–2: protection philosophy and grid-code compliance review with the grid operator; arc-flash study commissioned.
- Months 3–5: factory assembly and integration with container vendor's EMS; FAT witnessed by SGS with full test records.
- Month 6: shipment and installation alongside container erection; secondary injection and intertrip verification.
- Month 7: hot commissioning, grid-code compliance tests and handover to the operations contractor.
Results
- Energized on the grid operator's programme date; frequency-response performance four times faster than the grid code minimum.
- Lender's technical advisor accepted the documentation package without a comment round.
- First year: zero switchgear-attributed trips across more than 3,000 dispatch cycles.
“The documentation was the make-or-break for our lender. Funator's FAT pack arrived complete — SGS witness signatures and all — before the containers left the factory.” — Project Finance Director, BESS developer