Renewable Energy Case Study — Southeast Asia — Island Grid

200 MWh BESS Grid Stability Project — Southeast Asia — Island Grid

An island grid operator contracted a 100 MW / 200 MWh battery storage plant to provide frequency regulation and evening peak support on a network previously dependent on diesel and aging thermal units. The plant inter connects at 33kV and responds to grid operator dispatch signals in under a second.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
200 MWh BESS Grid Stability Project — Southeast Asia — Island Grid

Project Overview

Funator supplied the MV interconnection and LV switchboards interfacing the battery containers — plus the documentation package the lender's technical advisor required before financial close of the operation phase.

The Challenge

BESS electrical packages have their own physics:

  • Bidirectional rapid duty: the switchgear sees full-power reversal several times per hour — thermal cycling and protection coordination must be designed for it, not assumed.
  • Arc-flash exposure: DC-side fault energy plus inverter contribution demanded a documented arc-flash mitigation approach from day one.
  • Lender documentation: UL 9540 / IEC 62933-aligned declarations, witnessed FAT and metering-point definitions were conditions of financial close.

The Solution

Okken LV switchboards were configured for the skid interfaces, rated for the rapid duty cycle with temperature-monitored connections. MVnex 33kV panels connected the plant to the grid with directional protection and anti-islanding logic coordinated with the inverters' grid-forming controls. SGS witnessed the FAT, and the complete compliance pack was issued before shipment.

Equipment Qty / Configuration Key Ratings
Okken LV switchboardsOkken LV switchboards 6 × skids Up to 5000 A · rapid-duty rated · thermal monitoring
MVnex 33kV switchgear 4 × panels 1250 A · 31.5 kA/3s · directional protection
Sepam / MiCOM relays Protection suite Anti-islanding · ROCOF · intertrip with EMS
Compliance package UL 9540 / IEC 62933 Witnessed FAT · metering points · arc-flash study

Execution & Delivery

  • Months 1–2: protection philosophy and grid-code compliance review with the grid operator; arc-flash study commissioned.
  • Months 3–5: factory assembly and integration with container vendor's EMS; FAT witnessed by SGS with full test records.
  • Month 6: shipment and installation alongside container erection; secondary injection and intertrip verification.
  • Month 7: hot commissioning, grid-code compliance tests and handover to the operations contractor.

Results

  • Energized on the grid operator's programme date; frequency-response performance four times faster than the grid code minimum.
  • Lender's technical advisor accepted the documentation package without a comment round.
  • First year: zero switchgear-attributed trips across more than 3,000 dispatch cycles.
“The documentation was the make-or-break for our lender. Funator's FAT pack arrived complete — SGS witness signatures and all — before the containers left the factory.” — Project Finance Director, BESS developer
Explore the Renewable Energy solution Configuration guidance, standards and product lineup for this industry.
Renewable Solution