Industrial Manufacturing Case Study — Europe — Germany

Industrial Plant LV Retrofit — Europe — Germany

A German automotive plant was retrofitting its LV main distribution after decades of piecemeal additions had left the switchroom undocumented, overcrowded and impossible to maintain safely. Production ran 24/5 with weekend maintenance windows — the only slots available for cutover.

Pad-mounted electrical equipment at the base of onshore wind turbines with service technician
Industrial Plant LV Retrofit — Europe — Germany

Project Overview

Funator supplied a complete BlokSeT main distribution with PrismaSeT control cabinets, fully type-tested to IEC 61439, and planned the cutover with the plant's electrical team window by window.

The Challenge

Retrofit under a running plant is choreography:

  • Weekend-only cutover windows: each feeder transfer had to be completed, tested and handed back before Monday's first shift.
  • Legacy documentation gaps: circuits had to be traced and verified on site before design freeze.
  • Compliance: CE marking and IEC 61439 design verification required for insurance and audit purposes.

The Solution

The new lineup was factory-built with verified design (IEC 61439 Annex A testing), and feeders were pre-terminated on both sides so each weekend window became a rehearsed sequence: isolate old, land new, secondary injection, functional test, hand back. PrismaSeT cabinets carried the plant's control logic, pre-wired and FAT-tested as a system.

Equipment Qty / Configuration Key Ratings
BlokSeT main distribution 1 × lineup 4000 A · Form 4b · verified design
PrismaSeT control cabinets 12 × cabinets Pre-wired · FAT-tested with MCC logic
Cutover kits Per-feeder Pre-fab jumpers · labels · test records
Compliance pack CE + IEC 61439 Annex A design verification certificates

Execution & Delivery

  • Survey: legacy circuits traced, verified and documented — the as-built baseline.
  • Build: factory assembly and FAT including functional tests with plant I/O simulation.
  • Cutover: 6 weekend windows, each closed out with signed test records.
  • Close-out: full documentation handover; spares package agreed for 10-year support.

Results

  • Two years of operation since cutover with zero switchgear downtime.
  • Every window handed back on time — no Monday-morning production impact.
  • Insurance audit passed on the first visit with the new documentation pack.
“Documentation, certification and delivery were exactly as specified — no surprises.” — Plant Electrical Manager