Project Overview
Funator supplied a complete BlokSeT main distribution with PrismaSeT control cabinets, fully type-tested to IEC 61439, and planned the cutover with the plant's electrical team window by window.
The Challenge
Retrofit under a running plant is choreography:
- Weekend-only cutover windows: each feeder transfer had to be completed, tested and handed back before Monday's first shift.
- Legacy documentation gaps: circuits had to be traced and verified on site before design freeze.
- Compliance: CE marking and IEC 61439 design verification required for insurance and audit purposes.
The Solution
The new lineup was factory-built with verified design (IEC 61439 Annex A testing), and feeders were pre-terminated on both sides so each weekend window became a rehearsed sequence: isolate old, land new, secondary injection, functional test, hand back. PrismaSeT cabinets carried the plant's control logic, pre-wired and FAT-tested as a system.
| Equipment | Qty / Configuration | Key Ratings |
|---|---|---|
| BlokSeT main distribution | 1 × lineup | 4000 A · Form 4b · verified design |
| PrismaSeT control cabinets | 12 × cabinets | Pre-wired · FAT-tested with MCC logic |
| Cutover kits | Per-feeder | Pre-fab jumpers · labels · test records |
| Compliance pack | CE + IEC 61439 | Annex A design verification certificates |
Execution & Delivery
- Survey: legacy circuits traced, verified and documented — the as-built baseline.
- Build: factory assembly and FAT including functional tests with plant I/O simulation.
- Cutover: 6 weekend windows, each closed out with signed test records.
- Close-out: full documentation handover; spares package agreed for 10-year support.
Results
- Two years of operation since cutover with zero switchgear downtime.
- Every window handed back on time — no Monday-morning production impact.
- Insurance audit passed on the first visit with the new documentation pack.
“Documentation, certification and delivery were exactly as specified — no surprises.” — Plant Electrical Manager